Project Limits:
Beginning 150' west of Red Clay Creek to 150 feet east of Red Clay Creek / Wilmington Western RR.
Project Need:
Deterioration of the existing concrete deck of Bridge 1-148A has caused the bridge to become structurally deficient. Bridge 1-148B is a corrugated metal pipe with significant corrosion and 100% section loss at the waterline at several locations.
Project Overview:
This project involves the rehabilitation of Bridges 1-148A&B. The work includes replacing the existing concrete deck with a new concrete deck and barriers, minor repairs of the substructure, cleaning and painting the existing steel members, and minor approach roadway work for Bridge 1-148A. Additional work includes lining Bridge 1-148B with a pipe liner. The work will be performed under a full road closure with detour for vehicles. Pedestrian access will be maintained during construction.
Project Timeline:
Design Phase:
Design work to be completed no later than Spring 2018.
Construction Phase:
Construction work to be completed Spring 2019.
Additional Comments:
Anticipated Construction duration is 150 days. Construction and detour will be coordinated with detour for T201500103 Intersection Improvements for RT41 and Foulk Road.