Jason P Zern P.E. Operations Engineer NCC Public Works
We would like to request , re request & re re request
From the May 20 2024 Meeting New Castle County Little Mill Creek Stream Restoration / NCC Woodland Run Park as well as previously requested documents reports & or work products resulting from or about similar products .
- Presentation , Powerpoint
- Boards, Digital copy of
- Proposed Plans
- Engineering Reports
We have repeatedly requested information over the past several years on the Little Mill Creek Stream Restoration project with no avail .
I have the below two slides Neither of which has enough detail scale granularity fidelity or metrics for any reasonable person to make a determination much less an assessment or conclusion leading to an impression much less a decision .
Jason
We would like to request , re request & re re request
From the May 20 2024 Meeting New Castle County Little Mill Creek Stream Restoration / NCC Woodland Run Park as well as previously requested documents reports & or work products resulting from or about similar products .
- Presentation , Powerpoint
- Boards, Digital copy of
- Proposed Plans
- Engineering Reports
We have repeatedly requested information over the past several years on the Little Mill Creek Stream Restoration project with no avail .
I have the below two slides Neither of which has enough detail scale granularity fidelity or metrics for any reasonable person to make a determination much less an assessment or conclusion leading to an impression much less a decision .
The above images are illustrative Art not proposed plans .
The odd parProposed Plans NCC Little Mill Creek Stream Restoration Project .
We can not fathem why there would be NINE Proposed Plans NCC Little Mill Creek Stream Restoration Project over multiple years and not one bit of sharing of these plans with the community , nor request for feed back & discussion from the community regarding Proposed Plans NCC Little Mill Creek Stream Restoration Project .
After extensive discution with those in attendance of the 20 May New Castle County Little Mill Creek Stream Restoration / NCC Woodland Run Park Comunity meeting
What we walked away from the Meeting Impression wise or feeling about the RKK Proposed Plans for New Castle County Little Mill Creek Stream Restoration / NCC Woodland Run Park
-The Greenbank Mill is a lovely location for a gathering
- RKK did a very nice presentation but some what lacking in detail .
As communities effected understand it now …...
- There is going to be a 90’ Swath of swale & creek bed cut from Faulkland Road to 141
- This would some what deforest NCC Woodland Run Park as roughly illustrated in the above maps with aproxamat 90’ swaths illustrated .
THERE WOULD BE NO PARK LEFT AT NCC Woodland Run Park !
- The Comunities that use the NCC Woodland Run Park would be left with deforested drainage ditch with un shaded walking paths .
Of Note :: Since December 2019 to May 2024 300+ Standing Deadwood / Downed Deadwood Ash bore effected trees have been removed from NCC Woodland Run Park , Trees Forest shade all have become slightly more valuable to the community
- As far as ecology aquatic wildlife habitat Flora & Fauna -
"we have found it tends to come Back “
was RKK answer
I will spare you the full list but we have gotten used to living with Frogs , Toads , Fish , Crayfish , Snakes , Snails, Mice , Moles , Voles Deer , Foxes , Raccoons ,Possums ,Squirrels, Chipmunks , Groundhogs , Coyotes with more than 80 Species Of Birds Including Hawks, Herring Cranes , Turkeys , Eagles , & the Beaver Named Duncan Wood.
We have grown quite accustomed and come to appreciate living amongst the wildlife we would hate to see it, disturbed in such a drastic fashion unnecessarily.
New Castle County Woodland Run Park & the Little Mill Creek is currently a functional ecosystem a Riparian zone we would hate to see this destroyed.
I am sure withe the inclusion of the community in the process we can come up with a plan for the New Castle County Little Mill Creek Stream Restoration in NCC Woodland Run Park
Unfortunately it does not seem that the above proposed plan presented on 20 May by RKK will receive the support from the community.
We look forward to developing a new plan for New Castle County Little Mill Creek Stream Restoration / NCC Woodland Run Park with community support moving forward.
Your attention in these matters are much appreciated .
Feel free too reach out 302-463-2239 with any questions or clarification