2014 Brookland Terrace Del-DOT Maintenance Issues - Updated 23 September 2014


2014 Brookland Terrace Del-DOT Maintenance Issues List 



- Updated 23 September 2014




2014 Brookland Terrace Del-DOT Maintenance Issues List




Storm Drains



106 Hillside Ave at Brookland 
FIXED 11 JULY











EB 2900 Block Centre Ferris Road at Armstrong - at Gettier  - Reported March 2014 
- Steel Cover Plate week of 15 Sept 2014 



SB Centerville Road at Greenbank Road - Reported March 2014 FIXED 17 JULY



300 Armstrong Mid Block - Reported April 2014



400 NB Centerville Road  - Reported April 2014  Del-Dot " The catch basin at approximately 420 is currently plated and is assigned to our drainage contract.  There are about a dozen locations ahead of it on our schedule but we anticipate repairs to be complete by the end of August." Fixed 19-20 August 2014



Fixed 400 NB Centerville Road  - Reported April 2014 Del-Dot " The catch basin at approximately 420 is currently plated and is assigned to our drainage contract.  There are about a dozen locations ahead of it on our schedule but we anticipate repairs to be complete by the end of August." Fixed 19-20 August 2014




Pot Holes



Albany Place - Reported April 2014 FIXED 16 JULY


Maryland at Ohio - Reported April 2014 Fixed Ish Week 4 August Issues with Patch



Armstrong 300 Block at Speed Bump - Reported April 2014




Sink Hole



Armstrong Middle of 300 Block - Reported April 2014 - work order # 622469"Del-Dot " The location is scheduled for video this week assuming the weather holds.  We believe the issue may be with a sewer or water line.  I’ll update you once the video is complete in terms of findings and patch forward."




Curb Issues 


- North Woodward Ave at Virginia Ave 23 Sept 2014










Sinking Curb 100 Armstrong Ave -  Reported April 2014


Del-DOT "The damage appears to be the result of a water line issue.  It appears to have been marked but we are waiting for confirmation through Public Works on the status of the repair work by the utility.  It is our expectation that they should have fixed this curb if they have already made their repair but if it is still pending we will make sure Public Works is aware of the need to replace this section.  I’ll circle back with you once they can determine the status with the utility."




Uncompleted Utility Repaving





200 Vermont Ave Reported May 2014 FIXED wo 10 JULY



400 Block Ohio - Reported May 2014- Del-DOT" there is a permit “NC-0177-14G” in the system for this project submitted in May 2014, we will be inspecting the work" Fixed  18 Sept 2014




400 Armstrong Ave - Reported May 2014  Fixed Week 30 July DEl-DOT " there is a section of curb to be repaired by Artesian Water, they are going to send someone out to assess it. There is a future road project in this area, we will coordinate with the project to ensure we get the curb replaced in time."



605 Hillside Ave   - Reported May 2014
FIXED 17 JULY






Signage 












Brookland Terrace Sign replaced  with incorrect spelling Brooklyn Terrace -

Correct Spelling is Brookland Terrace -  Reported 11 July 2014 - signage down reported March
2014





Guard Rail



141 Centre -Ferris Road at North Woodward Ave - Reported 5 July 2014 Fixed Week 4 August




Bridge Lights Out









BR1-640 Route 2 at Centerville - Reported March 2014  Fixed Week 30 July / #4 Light Out NB Fixed Week of 2 September 2014 - Reported 23 Sept #5 Light out SB Centerville



BR1-606 141 at Centerville - Reported March 2014 
Fixed Week 30 July

17.9.14

BTCC Meeting 
7:30 PM Tuesday September 23rd 2014

Brookland Terrace Civic Club
Next Meeting 


7:30 PM Tuesday  September 23rd 2014

Marbrook Elementary School - 2101 Centerville Road







5.9.14

Brookland Terrace Civic Club Pavement Marking Request Centerville Road / Greenbank - Faulkland Rd.

With the upcoming repaving of Centerville Road we saw some areas that needed updated pavement markings to improve longstanding safety concerns .

- Trenton - Albany - NO Parking pavement markings with striping with No Parking spelled out 

- Albany - Brookland No parking pavement markings with striping with No Parking spelled out on south half of block & Turn Lane pavement markings with a bank on remaining north half of block . (this is a two house block )

 


      Some thing similar to this striping but with No Parking spelled out

This two blocks of no parking has been there for 30+ years all 4 residents agreed to the above .

 
Example of tapering requested 

Brookland Ave connects with Centerville Road at a awkward angle with poor visibility , turn lane bank would allow for safer entrance to Brookland Ave  via NB Centerville Road

Brookland Ave - Faulkland Road  similar to current markings but with Pavement Markings tapered to the corner allowing good sight lines when exiting .

- Yellow No Parking with striping with No Parking spelled out at bus stops Vermont Ave bus stop bus shelter in the 600 block of NB Centerville Rd

There is existing no parking at Vermont Ave bus stop & at bus shelter in the 600 block of NB Centerville Rd.

- Marbrook School Yellow No Parking with striping with No Parking spelled out Pavement Markings on the SB side Centerville where there is no parking currently   .

This no parking zone on SB Centerville at Marbrook entrances in conjunction with strict enforcement of the use of the student pick up lane has greatly improve visibility for crossing guards .

- Pedestrian cross walks preserved as they currently are from Greenbank - Faulkland Road

- There is currently a lack of handicapped curb access at Marbrook School .

Will the lack of handicapped curb cut be addressed prior to or during the repaving ?

2014 Brookland Terrace Del-DOT Maintenance Issues List - Updated 5 September 2014

2014 Brookland Terrace Del-DOT Maintenance Issues List 

- Updated 5 September 2014



2014 Brookland Terrace Del-DOT Maintenance Issues List

Storm Drains

106 Hillside Ave at Brookland 
FIXED 11 JULY




EB 2900 Block Centre Ferris Road at Armstrong - at Gettier  - Reported March 2014

SB Centerville Road at Greenbank Road - Reported March 2014 FIXED 17 JULY

300 Armstrong Mid Block - Reported April 2014

400 NB Centerville Road  - Reported April 2014  Del-Dot " The catch basin at approximately 420 is currently plated and is assigned to our drainage contract.  There are about a dozen locations ahead of it on our schedule but we anticipate repairs to be complete by the end of August." Fixed 19-20 August 2014

Fixed 400 NB Centerville Road - Reported April 2014 Del-Dot " The catch basin at approximately 420 is currently plated and is assigned to our drainage contract. There are about a dozen locations ahead of it on our schedule but we anticipate repairs to be complete by the end of August." Fixed 19-20 August 2014

Pot Holes

Albany Place - Reported April 2014 FIXED 16 JULY

Maryland at Ohio - Reported April 2014 Fixed Ish Week 4 August Issues with Patch


Armstrong 300 Block at Speed Bump - Reported April 2014

Sink Hole

Armstrong Middle of 300 Block - Reported April 2014 - work order # 622469"Del-Dot " The location is scheduled for video this week assuming the weather holds.  We believe the issue may be with a sewer or water line.  I’ll update you once the video is complete in terms of findings and patch forward."

Curb Issues 




Sinking Curb 100 Armstrong Ave -  Reported April 2014

Del-DOT "The damage appears to be the result of a water line issue.  It appears to have been marked but we are waiting for confirmation through Public Works on the status of the repair work by the utility.  It is our expectation that they should have fixed this curb if they have already made their repair but if it is still pending we will make sure Public Works is aware of the need to replace this section.  I’ll circle back with you once they can determine the status with the utility."

Uncompleted Utility Repaving


200 Vermont Ave Reported May 2014 FIXED wo 10 JULY

400 Block Ohio - Reported May 2014- Del-DOT" there is a permit “NC-0177-14G” in the system for this project submitted in May 2014, we will be inspecting the work"




400 Armstrong Ave - Reported May 2014  Fixed Week 30 July DEl-DOT " there is a section of curb to be repaired by Artesian Water, they are going to send someone out to assess it. There is a future road project in this area, we will coordinate with the project to ensure we get the curb replaced in time."

605 Hillside Ave   - Reported May 2014
FIXED 17 JULY


Signage 




Brookland Terrace Sign replaced  with incorrect spelling Brooklyn Terrace -
Correct Spelling is Brookland Terrace -  Reported 11 July 2014 - signage down reported March 2014

Guard Rail

141 Centre -Ferris Road at North Woodward Ave - Reported 5 July 2014 Fixed Week 4 August

Bridge Lights Out



BR1-640 Route 2 at Centerville - Reported March 2014  Fixed Week 30 July / #4 Light Out NB Fixed Week of 2 September 2014

BR1-606 141 at Centerville - Reported March 2014
Fixed Week 30 July

3.9.14

CLNCC 2014 Candidates Forum September 16, 2014 6:30-9:00 pm. at Cranston Heights Fire Company 3306 Kirkwood Hwy, Wilmington, DE 19808

Civic League for New Castle County 2014 Candidates Forum




September 16, 2014 6:30-9:00 pm.

Cranston Heights Fire Company  3306 Kirkwood Hwy, Wilmington, DE 19808

http://www.civicleagueforncc.org

president@civicleagueforncc.org